Construction and upgrades are in progress at 28 district schools.  Here’s a rundown of the projects.

Remodel and expansion projects

  • Columbia River High School: Final design phase of remodel and expansion; construction scheduled to begin winter 2020
  • Early Childhood Special Education assessment center: Will move to remodeled McLoughlin classroom pod; remodel scheduled to begin spring 2020
  • Eisenhower Elementary School: Construction of two new K-3 classroom additions underway
  • Felida Elementary School: Construction of five new K-3 classroom additions and remodeled restrooms underway
  • Franklin Elementary School: Going to bid for expansion of parking lot, classroom additions and elimination of portables; construction to begin November 2019
  • Fruit Valley Community Learning Center: Construction currently underway of four K-3 classroom additions
  • Harney Elementary School: Four new K-3 classroom additions completed; secure entry and Family-Community Resource Center renovation underway
  • Lieser School: Programs will move to remodeled Marshall building; remodel scheduled to begin spring 2020
  • Sacajawea Elementary School: Final design phase of remodel and expansion; project out to bid
  • Salmon Creek Elementary School: Two new K-3 classroom additions completed August 2019
  • Vancouver School of Arts and Academics: Final design phase of remodel and expansion; construction to begin spring 2020

New and replacement schools

  • Fir Grove: In final design phase of new replacement school; construction to begin January 2020
  • Martin Luther King Jr. Elementary School: New replacement school under construction; scheduled to open fall 2020
  • Marshall Elementary School: Construction underway; scheduled to open spring 2020
  • McLoughlin Middle School: Construction underway; scheduled to open spring 2020
  • Ogden Elementary School: New replacement school opened Aug. 27, 2019
  • Truman Elementary School: Under construction; scheduled to open fall 2020
  • Vancouver Innovation, Technology and Arts Elementary School: Final design phase of new school; construction to begin January 2020
  • Vancouver iTech Preparatory: New school under construction; scheduled to open January 2020
  • Walnut Grove Elementary School: Design phase of new replacement school is complete; construction to begin November 2019

Upgrades and improvements

  • Hazel Dell Elementary School: In design phase of Family-Community Resource Center renovation, roof replacement and HVAC upgrades
  • Hough Elementary School: Addition of HVAC/air conditioning and replacement of windows to begin spring 2020; currently in design phase of Family-Community Resource Center renovation and secure entry
  • Jason Lee Middle School: In final design phase of classroom and Family-Community Resource Center improvements and secure entry
  • Jefferson Middle School: Safety improvements in parking lot
  • Kiggins Bowl Stadium: In design phase for upgrades to stadium, concessions, restrooms and new turf currently; track feasibility study in progress
  • Lincoln Elementary School: Renovation of Family-Community Resource Center; secure entry, HVAC and exterior lighting improvements; scheduled for summer 2020
  • Minnehaha Elementary School: Addition of secure entry scheduled spring/summer 2020
  • Roosevelt Elementary School: Renovation of Family-Community Resource Center, secure entry; scheduled spring/summer 2020

All school construction and upgrade projects are paid for with funding from the bond measure passed by voters in February 2017.

View the full scope of bond construction and upgrade projects.